Regional development through energy infrastructure: A comparison and optimization of Iran-Pakistan-India (IPI) & Turkmenistan- Afghanistan-Pakistan-India (TAPI) gas pipelines

Authors

  • Yousaf Ali School of Management Sciences, GIK Institute of Engineering Sciences and Technology, Topi, Swabi, KP, Pakistan
  • Manzoor Ahmad Faculty of Mechanical Engineering, GIK Institute of Engineering Sciences and Technology, Topi, Swabi, Pakistan
  • Muhammad Sabir NUST Business School (NBS), National University of Sciences and Technology (NUST), Islamabad, Pakistan
  • Sajjad Ali Shah Faculty of Mechanical Engineering, GIK Institute of Engineering Sciences and Technology, Topi, Swabi, Pakistan

DOI:

https://doi.org/10.31181/oresta091221082a

Keywords:

Optimization models, Fuzzy TOPSIS, Fuzzy CPM, Genetic Algorithm, MCDM, TAPI, IPI, Pipelines

Abstract

Pakistan is working on two pipeline projects, namely, Iran-Pakistan-India (IPI) and Turkmenistan-Afghanistan-Pakistan-India (TAPI) gas pipelines, to meet its energy supply-demand gap. This study's aims to compare these two projects and identify the most suitable option for Pakistan. Furthermore, as the TAPI project is progressing faster than the IPI project, this study also aims to identify the critical activities associated with TAPI projects. Finally, a model is proposed to optimize the material and transportation costs related to the TAPI project. The study's contribution by using fuzzy set theory-based multi-criteria decision-making (Fuzzy MCDM) to compare two projects along with usage of the Fuzzy Critical Path Method (FCPM) for the identification of critical activities associated with the TAPI project. Finally, the Genetic Algorithm is applied to optimize the material and transportation costs of the TAPI project. The results show that IPI has advantages over TAPI in terms of power generation, transportation cost, transits fee, and gas prices. The critical path analysis of the TAPI gas pipeline shows that it will take approximately 75 to 330.5 weeks to complete.  The study is useful for the managers who have to work in these projects, the policymakers considering these projects at various levels, and the researcher having an interest in applying Fuzzy set theory with MCDM, CPM, and in the context of the energy infrastructure.

Downloads

Download data is not yet available.

References

Abbas, M. N., 2015. Energy crisis in Pakistan. Masters Thesis: Naval Postgraduate School, Monterey, California, the USA.

ADB, 2012. Turkmenistan–Afghanistan–Pakistan–India Natural Gas Pipeline Project, Phase 3, Research and Development Technical Assistance (RDTA): Asian Development (ADB), Manila, Philippines.

ADB, 2020. Proposed Loan, Grant, Partial Credit Guarantee, and Transaction Technical Assistance Turkmenistan-Afghanistan-Pakistan-India (TAPI), Asian Development Bank (ADB): Concept Paper, Project Number: 52167-001.

Ali, Y., Abdullah, M. & Khan, A. U., 2019. The best manufacturing procedure for the commercial production of urea, using AHP based TOPSIS. International Journal of the Analytic Hierarchy Process, 11(3), 313-330.

Ali, Y., Bin Saad, T., Sabir, M., Muhammad, N., Salman, A. & Zeb, K., 2020a. Integration of green supply chain management practices in the construction supply chain of CPEC. Management of Environmental Quality: An International Journal, 31(1), 185-200.

Ali, Y., Rahman, A., Lala, S., & Sabir, M. (2021). Economic viability of foreign investment in public transport of Pakistan–orange line metro train in focus. Transnational Corporations Review, 13(3), 321-333.

Ali, Y., Sabir, M., Bilal, M., Ali, M., & Ali, Khan, A. 2020b. Economic viability of foreign investment in railways: a case study of the China-Pakistan Economic Corridor (CPEC). Engineering Economist, 65(2), 158-175.

Ali, Y., Sabir, M. & Noor, M., 2019. Refugees and host country nexus: a case study of Pakistan. Journal of International Migration and Integration, 20(1), 137-153.

Ali, Y., Saleem, S. & Sabir, M., 2020a. Structural decomposition analysis to investigate the changes in energy consumption in Pakistan. Journal of Systems Science and Complexity, 33, 1497–1515

Anceschi, L., 2017. Turkmenistan and the virtual politics of Eurasian energy: the case of the TAPI pipeline project. Central Asian Survey, 36(4), 409-429.

Aziz, R., 2013." Optimizing strategy software for repetitive software projects within multi-mode resources." Alexandria Engineering Journal, 1(52), 373-385.

Baluch, M. U. F., 2012. Pakistan-Iran pipeline project – A liberal approach. Institute for Strategic Studies, Research, and Analysis (ISSRA), 4(2), 119-140.

Bilal M., Ali Y., Sabir M., Petrillo A., De Felice F. (2021). A Multi-Criteria Cost-Benefit Analysis to optimize the oil supply networks. Proceedings of the 20th International Conference on Modeling & Applied Simulation (MAS 2021), pp. 91-103. DOI: https://doi.org/10.46354/i3m.2021.mas.012

Bin Hameed, H., Ali, Y. & Khan, A. U., 2020. Regional Development through Tourism in Balochistan under the China-Pakistan Economic Corridor. Journal of China Tourism Research, published online: doi.org/10.1080/19388160.2020.1787910.

Ching, H. & Kwangsun, Y., 1981. Methods for Multiple Attribute Decision Making. In: 1st, ed. Lecture Notes in Economics and Mathematical Systems. Berlin Heidelberg: Springer-Verlag, 58-191.

The company, S. S. G., 2007. Public Listed large scale company. [Online] Available at: https://www.ssgc.com.pk/web/?p=5764 [Accessed November 22, 2019].

D'Souza, S. M., 2017. TAPI pipeline: A Confidence Building Measure for South Asia. Focus on Defense and International Security, December 1(525), 4-6.

Dijkman, T. J., Haeringen, H. v. & Lange, S. d., 1983. Fuzzy numbers. Journal of Mathematical Analysis and Applications, 92(2), 301-341.

Eraslan, S. & Karaaslan, F., 2015. A group decision-making method based on TOPSIS under a soft fuzzy environment. Journal of new theory, 1(3), 30-40.

Ertuğrul, İ. & Karakaşoğlu, N., 2008. Comparison of fuzzy AHP and fuzzy TOPSIS methods for facility location selection. 783-795, 39(7-8), 783–795.

Galeano, H. & Narváez, P., 2003. Genetic Algorithms for the optimization of the pipeline systems for liquid transportation. Ciencia, Tecnología y Futuro, 2(4), 55-64.

Goldberg, D. E., 1989. Genetic Algorithms in Search, Optimization and Machine Learning. 1st ed. Boston: Addison-Wesley Longman Publishing Co., Inc. Boston, MA, USA.

Goldberg, D. E. & Richardson, J., 1987. Genetic algorithms with sharing for multimodal function optimization. In: J. J. Grefenstette, ed. Proceedings of the Second International Conference on Genetic Algorithms on Genetic algorithms and their application. Hillsdale: L. Erlbaum Associates Inc. Hillsdale, NJ, USA, 41-49.

Gopal, N., & Panchal, D. (2021). A structured framework for reliability and risk evaluation in the milk process industry under fuzzy environment. Facta Universitatis, Series: Mechanical Engineering.

Habibi, Birgani, Koppelaar & Radenović, 2018. Using fuzzy logic to improve the project time and cost estimation based on Project Evaluation and Review Technique (PERT). Journal of Project Management, 3(4), 183-196.

Haq, ul, N., 2010. Iran-Pakistan Peace Pipeline. Islamabad Policy Research Institute (IPRI): Islamabad, Pakistan.

Hudaa, S. M. & Ali, H. S., 2017. Energy diplomacy in South Asia: Beyond the security paradigm in accessing the TAPI pipeline project. Energy Research & Social Science, 34, 202-213.

ISGS, 2020. Inter-State Gas Systems (ISGS) (pvt) Ltd, Pakistan. [Online] Available at: http://isgs.com.pk/projects/tapi/ [Accessed July 30 2020].

Izadi, Ranjbarian, Saeedeh & Mofakham, 2013. Performance Analysis of Classification Methods and Alternative Linear Programming Integrated with Fuzzy Delphi Feature Selection. I.J. Information Technology and Computer Science, 10(2), 9-20.

Joshi, M., 2011. Turkmenistan-Afghanistan Pakistan-India pipeline possibility or pipe dream? Gateway House: Indian Council on Global Relations, Mumbai, India.

Khan, A., 2012. IPI pipeline and its implications on Pakistan. Strategic Studies, 32(2-3), 102-113.

Khan, F., Ali, Y. & Khan, A. U., 2020. Sustainable hybrid electric vehicle selection in the context of a developing country. Air Quality, Atmosphere & Health, 13, 489–499.

Khetran, M. S., 2017. Turkmenistan-Afghanistan-Pakistan-India (TAPI) Gas Pipeline: Policy brief. Institute of Strategic Studies, Islamabad: Pakistan.

Khetran, M. S. (2020). Pakistan-Turkmenistan Relations: Evaluating the Progress on TAPI. Strategic Studies, 40(2).

Kulkarni, S. S., 2016. India's Decision Making on Cross-Border Natural Gas Pipelines (1989–2012). Strategic Analysis, 5(40), 405-424.

Lee, Y., 2014. Opportunities and risks in Turkmenistan's quest for diversification of its gas export routes. Energy Policy, 74, 330-339.

Liberatore & Matthew, 2002. A fuzzy approach to critical path analysis. Project Management Institute, Newtown Square, PA, Seattle, USA.

Mahmood, A. et al., 2014. Pakistan's overall energy potential assessment, comparison of LNG, TAPI and IPI gas projects. Renewable and Sustainable Energy Reviews, 31, 182-193.

Mares, M., 2006. Fuzzy sets. Scholarpedia, 1(10), 20-31.

Mazhar, M. S. & Goraya, N., 2013. Challenges In Iran-Pakitan Gas Pipieline. NDU Journal, 28(1), 163-178.

Minatour, Y., Bonakdari, H., Zarghami, M. & Bakhshi, M. A., 2015. Water supply management using an extended group fuzzy decision-making method: a case study in north-eastern Iran. Applied Water Science, 5(3), 291-304.

Mitchell, M., 1996. An introduction to genetic algorithms. MIT Press: The USA.

MoF, 2007. Economic Survey of Pakistan 2006-07, Ministry of Finance, Government of Pakistan: Islamabad, Pakistan.

MoF, 2020. Economic Survey of Pakistan 2019-20, Ministry of Finance, Government of Pakistan, Islamabad, Pakistan.

Munir, M., Ahsan, M. & Zulfqar, S., 2013. Iran-Pakistan Gas Pipeline: Cost-Benefit Analysis. Journal of Political Studies, 20(2), 161-178.

Naseem, A. M., 2015. Energy crisis in Pakistan, Baluchistan: Monterey, California: Naval Postgraduate School.

Oilscams, 2018. Oilscams.org/gas-pipeline-construction. [Online] Available at: http://www.oilscams.org [Accessed December 5 2019].

Pandian, S. G., 2005. Energy trade as a confidence-building measure between India and Pakistan: a study of the Indo-Iran trans-Pakistan pipeline project. Contemporary South Asia, 14(3), 307-320.

Pradhan, S. K., 2020. The Way Forward. In: India's Quest for Energy Through Oil and Natural Gas. Springer: Springer Publisher.

Rajmil, D., Morales, L., & Andreosso-O’Callaghan, B. (2021). How realistic is the China–Pakistan–Iran economic corridor? Asian Journal of Comparative Politics, 20578911211041403.

Rajpoot, A. R., & Naeem, S. (2020). Geopolitics of Energy Pipelines: Case Study of TAPI and IP gas Pipelines. International Journal on Integrated Education, 3(8), 15-22.

Ramo, R. M., 2014. Fuzzy Pert For Project Management. International Journal of Advances in Engineering & Technology, 7(4), 1150-1160.

Rao, P. B. & Nowpada, R. S., 2012. Fuzzy Critical Path Method Based on Lexicographic Ordering. Pakistan Journal of Statistics and Operation Research, 8(1), 135-154.

Sadat, S. M., 2015. TAPI and CASA-1000: Win-Win trade between Central Asia and South Asia, Norwegian Institute of International Affairs: Norway.

Sahir, M. H. & Qureshi, A. H., 2007. Specific concerns of Pakistan in the context of energy security issues and geopolitics of the region. Energy Policy, 35(4), 2031-2037.

Saqib, M. Y., 2019. TAPI Project as a Role Model for Other National Development Projects of Afghanistan. International Journal of Recent Technology and Engineering (IJRTE), VII(6S5), 300-304.

Sheikh, K. A., 2019. Pakistan Economist. [Online] Available at: http://www.pakistaneconomist.com/2019/10/21/tapi-gas-pipeline-a-dream-project-for-pakistan-india/ [Accessed November 11 2019].

Singh, R. R. & Nain, P. K. S., 2012. Optimization of Natural Gas Pipeline Design and Its Total Cost Using GA. International Journal of Scientific and Research Publications, Volume 2, Issue 8, August 2012, 2(8), 1-10.

Stephanatos, B., 2014. https://sites.google.com/site/metropolitanforensics/basics-of-gas-compressor-stations. [Online] Available at: https://sites.google.com/site/metropolitanforensics [Accessed 5 12 2019].

Tung, C., 2000. Extensions of the TOPSIS for group decision-making under fuzzy environment. Fuzzy Sets and Systems, 114(1), 1-9.

Vahidi, J. & Rezvani, S., 2013. Arithmetic Operations on Trapezoidal Fuzzy Numbers. Journal of Non-linear Analysis and Application, 2013, 1-8.

Yadav, D. & Kumar, S., 2017. A Case Study on the Optimization of the Transportation Cost for Raipur steel and thermal power plant. International Journal for Research in Applied Science & Engineering Technology, 5(9), 768-776.

Zadeh, L., 1996. Fuzzy sets, fuzzy logic, and fuzzy systems: Selected papers by Lotfi A. Zadeh. 6 ed. World Scientific: Singapore.

Published

2021-12-09

How to Cite

Ali, Y., Ahmad, M. ., Sabir, M., & Shah, S. A. (2021). Regional development through energy infrastructure: A comparison and optimization of Iran-Pakistan-India (IPI) & Turkmenistan- Afghanistan-Pakistan-India (TAPI) gas pipelines. Operational Research in Engineering Sciences: Theory and Applications, 4(3), 82–106. https://doi.org/10.31181/oresta091221082a